Brunswick Road reopens today

Winter storms caused a portion of Brunswick Road to drop about 14 inches below the rest of the pavement. The broken section has now been repaired and is slated to reopen at 7 a.m. Thursday.
Submitted to The Union |

Brunswick Road reopened to all through traffic beginning today at 7 a.m., more than two weeks ahead of schedule.

Nevada County officials reported Tuesday that road repair work would be finished by Saturday, but later said the process is moving along even more quickly than they anticipated.

Hansen Brothers Enterprises expedited final road paving and striping work this week, which has resulted in the road reopening faster than expected, according to Joshua Pack, principal civil engineer for the Nevada County Department of Public Works.



Emergency repair work on Brunswick Road began July 15 and was originally expected to last about a month. Hansen Brothers Enterprises has installed additional drains and replaced about 4,000 cubic yards of roadway fill in order to address damages caused by this winter’s storms, Pack said.


Support Local Journalism


Support Local Journalism

Readers around Grass Valley and Nevada County make The Union’s work possible. Your financial contribution supports our efforts to deliver quality, locally relevant journalism.

Now more than ever, your support is critical to help us keep our community informed about the evolving coronavirus pandemic and the impact it is having locally. Every contribution, however large or small, will make a difference.

Your donation will help us continue to cover COVID-19 and our other vital local news.

 

Start a dialogue, stay on topic and be civil.
If you don't follow the rules, your comment may be deleted.

User Legend: iconModerator iconTrusted User