On Tuesday, the 200 block of North Auburn Street will be closed as city workers repair a lateral water line, city Utility Operations Manager Mike Healy said. A slow leak was detected there, Healy added.
As dry weather holds, road work continues elsewhere on Grass Valley roads through Nov. 11 as a city contractor moves ahead with street repairs and repaving.
Road affected are: Taylorville Road, between McKnight Way and Freeman Lane; Packard Drive, King Court, Kathleen Way, Delia Court, Blight Road, Todd Court, Penstock Drive, Pelton Way, Scadden Drive and Fawcett Street.
Motorists should watch out for workers between 7 a.m. and 7 p.m., weather permitting. Delays are expected to be minimal.
Meanwhile, work continues on Banner Mountain roads starting at 8 a.m. daily to install the Banner Cascade pipeline, the Nevada Irrigation District reported.
Construction this week is at the intersection of Banner Lava Cap Road and Wings of Morning Drive and is expected to take a few days to complete. Wings of Morning residents will need to continue using the Sesame Street detour, turning right onto Banner Lava Cap Road to avoid the construction delays.
Work to finalize appurtenances and culverts will continue along Wings of Morning this week and next after the raw water connection is completed. Detours will be set up to direct traffic around construction in order to avoid delays.
Treated water pipeline installation is set to begin the week of Nov. 7, weather permitting.
Construction at Madrone Forest Drive near the Idaho-Maryland Road intersection is starting this week, after the Wings of Morning Drive connection is completed. Raw water pipeline installation on the Overland section will connect to the existing pipeline on Madrone Forest Drive, blocking through traffic on Idaho-Maryland for up to 20 minutes.
If traveling east of Madrone Forest Drive on Idaho-Maryland Road, residents may use Banner Lava Cap Road and Old Tunnel Road to access Brunswick Road.
Treated water pipeline installation on Red Gate Road is scheduled to start this week.
Pavement installation is scheduled for Red Dog Cross Road, Lola's Echo Road and Oak Ridge Road through Wednesday.
For details on the Banner Cascade road work schedule, see below.
As dry weather holds, road work continues elsewhere on Grass Valley roads through Nov. 11 as a city contractor moves ahead with street repairs and repaving.
Road affected are: Taylorville Road, between McKnight Way and Freeman Lane; Packard Drive, King Court, Kathleen Way, Delia Court, Blight Road, Todd Court, Penstock Drive, Pelton Way, Scadden Drive and Fawcett Street.
Motorists should watch out for workers between 7 a.m. and 7 p.m., weather permitting. Delays are expected to be minimal.
Meanwhile, work continues on Banner Mountain roads starting at 8 a.m. daily to install the Banner Cascade pipeline, the Nevada Irrigation District reported.
Construction this week is at the intersection of Banner Lava Cap Road and Wings of Morning Drive and is expected to take a few days to complete. Wings of Morning residents will need to continue using the Sesame Street detour, turning right onto Banner Lava Cap Road to avoid the construction delays.
Work to finalize appurtenances and culverts will continue along Wings of Morning this week and next after the raw water connection is completed. Detours will be set up to direct traffic around construction in order to avoid delays.
Treated water pipeline installation is set to begin the week of Nov. 7, weather permitting.
Construction at Madrone Forest Drive near the Idaho-Maryland Road intersection is starting this week, after the Wings of Morning Drive connection is completed. Raw water pipeline installation on the Overland section will connect to the existing pipeline on Madrone Forest Drive, blocking through traffic on Idaho-Maryland for up to 20 minutes.
If traveling east of Madrone Forest Drive on Idaho-Maryland Road, residents may use Banner Lava Cap Road and Old Tunnel Road to access Brunswick Road.
Treated water pipeline installation on Red Gate Road is scheduled to start this week.
Pavement installation is scheduled for Red Dog Cross Road, Lola's Echo Road and Oak Ridge Road through Wednesday.
For details on the Banner Cascade road work schedule, see below.
Banner Cascade construction details
10/24/11 to 11/18/11■ Banner Lava Cap Road, between Red Gate Road and E. George WTP:
· Raw water pipeline installation is completed; testing will start in October.
· Final paving to be scheduled after completion of treated water installation on Red Gate Road.
■ Red Gate Road:
· Treated water pipeline installation is scheduled to begin the week of Oct. 31.
· Final paving to be scheduled after completion of treated water installation.
■ Overland from Madrone Forest Drive to Red Gate Road:
· Raw water pipeline installation to resume toward Madrone Forest Drive this week. Starting on Monday 10/31, traffic on Idaho Maryland Road will be impacted by delays up to twenty minutes during the connection to Madrone Forest Drive. Please use an alternate route, if possible.
■ Madrone Forest Drive: Final cleanup ongoing. No delays anticipated.
■ Overland between Madrone Forest Drive and the airport:
· Additional erosion control and hydroseed has been applied.
■ Airport and Loma Rica Water Treatment Plant:
· Erosion control and hydroseed has been applied.
■ Lee Lane:
· Erosion control and hydroseed has been applied.
■ Idaho Maryland Road, between Lee Lane and Banner Lava Cap Road:
· Restoration work has started and final hydroseed has been applied.
■ Banner Lava Cap Road, between Idaho Maryland Road and Wings of
Morning Drive:
· Restoration work has started and final hydroseed has been applied.
■ Wings of Morning Drive (WOMD):
· Connection of the 48 inch raw water pipeline to Banner Lava Cap Road pipeline will be completed this week. Watch for signage and flaggers to safely direct you through the construction zone. Delays are expected to be up to twenty minutes. WOMD area residents will need to continue using the Sesame Street detour while the connection is made.
· Work to finalize appurtenances and culverts will continue along WOMD this week and next after the raw water connection is completed. Detours will be set up to direct traffic around construction in order to avoid delays.
· Treated water pipeline installation to begin the week of November 7, weather permitting. Details of the installation will follow next week.
· Erosion control along the cut bank and gravel road will be installed along WOMD and will be maintained throughout the winter by NID.
■ Opalite Way/Snow Mountain Flow Control/Overland:
· Control building construction work is progressing.
· Raw water pipeline installation on Overland is completed.
■Red Dog Cross Road, Lola's Echo Road, and Oak Ridge Road:
· Pavement installation is scheduled to be underway next week on
Tuesday, November 1 and Wednesday, November 2.